Each angle is tied to what the City must find before it can approve, and each comes with a specific request. "Strong" means the records clearly support it now. "Solid" means it's well supported but needs one more document. "Supporting" means it strengthens the others.
1Strong
Require a full traffic study, counted on an assembly day
The 73.8-trip screening uses half the building at the weekday rate. The rate table it cites says to quadruple for assembly days: about 295 trips even for half the building, about 580 for all of it.
Ask: Reject the TIA-1 screening. Require a Local Transportation Analysis and a VMT analysis covering Sunday arrivals and departures at Via Cancion and Rancho Santa Fe Rd, queuing, the left-turn pocket, and the new median.
Findings 1 & 3 · SMC 20.400.160.B.6 · CEQA § 15332(d)
2Strong
Cap capacity by what Via Cancion can carry
The code says an assembly building's maximum capacity must be set by "the capacity of streets serving the facility." The plans route every car through Via Cancion, a narrow private road with one signalized exit.
Ask: The City must analyze Via Cancion's capacity (width, the single exit, signal timing, emergency use) and set any occupancy limit from that, not from room size.
SMC 20.400.160.B.6 · Findings 1 & 3
3Strong
Fire protection plan, evacuation analysis, and 150 ft clearance on site
Fire requires 150 ft of fuel modification on all sides, "on site and off site," plus a fire protection plan. None has been filed. Evacuation questions remain unanswered.
Ask: Deem the application incomplete until the fire protection plan and fuel-modification plan are filed. Require a written evacuation analysis for a full-attendance event during a Red Flag day. Don't let the project rely on clearance over neighbors' land.
Finding 1 · Fire Code / SMC 17.64 · CEQA wildfire factors
4Strong
No Class 32 exemption: require an Initial Study
Class 32 requires no significant traffic, noise, air, or water effects, no habitat value, and no "unusual circumstances." The records show a creek connection, deep fill over a drainage channel, Very High fire hazard, a single exit, and an assembly-day trip count far over the line.
Ask: Prepare an Initial Study, at minimum leading to a Mitigated Negative Declaration, and an EIR if the evidence supports one. Circulate it for public comment and trigger AB 52 tribal consultation.
CEQA Guidelines §§ 15332, 15300.2 · Finding 2
5Strong
Updated soils report for the actual design
The only soils report predates the design and assumed no below-ground level. The design now has a full lower level in up to 35 ft of unsuitable fill with groundwater at 12½–16 ft.
Ask: Require an updated geotechnical report for the current plan, plus a construction-impacts analysis (vibration from stone columns or deep grading, haul trips, hours, dust) and a Phase I environmental site assessment.
Finding 1 · Building Official 2025 comment · CEQA geology/hazards
6Solid
Biology, wetlands, and the creek
Runoff reaches a creek tributary to San Marcos Creek. The plans' hidden text says "Location of Steambed [sic]" and "Habitat Mitigation(?)". A biological assessment is listed on the intake checklist but wasn't released. The stormwater plan marks no natural features.
Ask: Release the Helix biological assessment. Require a biological resources report and a jurisdictional waters delineation. Correct the stormwater plan's natural-features checklist and route the project to Watershed review.
CEQA § 15332(c) · Finding 1
7Solid
Fix the parking math under San Marcos code
The plans cite a code section that isn't San Marcos's, count one room at a time, leave out 1,480 sq ft of the main room and 6,388 sq ft of covered outdoor space, and rely on a gravel overflow lot.
Ask: Recalculate under SMC Chapter 20.340, counting all assembly areas that could be used on the same day. No gravel overflow, no parking on Via Cancion, and any "not at the same time" claim written as an enforceable condition.
SMC 20.340 · Findings 1 & 3
8Solid
Get it all into the incompleteness letter
The City must say within 30 days of filing whether the application is complete and list what's missing. Fees were paid September 29.
Ask: List every missing item: traffic study, fire protection plan, fuel-modification plan, updated soils report, biology, water/sewer study, lighting plan, City environmental form, sign-posting proof, CEQA analysis, corrected setbacks and height.
Gov. Code § 65943 · SMC 20.520.030.D
9Solid
Judge the whole master plan, then cap it
"Master Plan" on every sheet, "mass graded pads for future development," an "amphitheater," and a 2023 concept at 25,592 sq ft.
Ask: The City should state the maximum build-out the grading allows and evaluate it now. Any approval should cap floor area at what's shown, with no outdoor amphitheater or amplified outdoor events. Any expansion would need a new CUP.
CEQA "whole of the action" (§ 15378) · Findings 1–3
10Solid
Via Cancion changes need their own review and notice
Widening to 24 ft, a sidewalk, utility undergrounding, and right-of-way easements on Via Cancion were all flagged by City staff. The Notice of Application mentions only Rancho Santa Fe Rd.
Ask: Describe all Via Cancion work in the project description, analyze it under CEQA, and coordinate with the County, since most of the street is in unincorporated County.
Findings 1 & 3 · CEQA project description
11Supporting
Hold the City to the 2003 promise
The 2003 rezoning was found compatible only because no development was proposed, and residents were promised full review of any future development.
Ask: Base the compatibility analysis on the low-density rural-residential character the 2003 record describes, not on the nursery.
Findings 2 & 3 · PC Resolution 03-3637
12Supporting
Same rules for every building: setbacks, height, solar
15-ft side setbacks vs. the 30-ft assembly-use rule, a 50-ft height area measured from the pre-dedication line, 48 sq ft above the envelope, and an opt-out from the solar requirement.
Ask: Verify every standard as the code is written. If the project can't meet one, it needs a formal variance or exception, with its own findings and public notice.
SMC 20.210.050 · 20.400.160 · Climate Action Plan E-2